Expansion of Hong Kong International Airport into a Three-Runway System |
|
Chapter
Title
Tables
The “Expansion of Hong Kong International
Airport into a Three-Runway System” (the Project) serves to meet the future air
traffic demands at Hong Kong International Airport (HKIA). On 7 November
2014, the Environmental Impact Assessment (EIA) Report (Register No.:
AEIAR-185/2014) for the Project was approved and an Environmental Permit (EP)
(Permit No.: EP-489/2014) was issued for the construction and operation of the
Project.
Airport Authority Hong Kong (AAHK) commissioned
Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental
Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A)
works during the construction phase of the Project in accordance with the
Updated EM&A Manual.
This is the 7th Construction Phase
Monthly EM&A Report for the Project which summarizes the monitoring results
and audit findings of the EM&A programme during the reporting period from 1
July 2016 to 31 July 2016.
Key Construction Activities in the Reporting
Month
The key construction activities of the Project
carried out in the reporting month were related to Contract P560(R) Aviation
Fuel Pipeline Diversion Works (Contract P560(R)) which involved installation of
horizontal directional drilling (HDD) casing, drilling of HDD pilot hole and
stockpiling of excavated materials from HDD operation. Site investigation
works were also carried out to support design process.
No construction work was carried out on Sheung Sha Chau Island during the ardeid’s
breeding season in the reporting month in accordance with the Updated EM&A
Manual.
EM&A
Activities Conducted in the Reporting Period
The monthly EM&A programme was undertaken
in accordance with the Updated EM&A Manual of the Project. During the
reporting period, the ET conducted thirty sets of air quality measurements,
twenty sets of construction noise measurements, as well as four environmental
site inspections, landscape & visual and waste monitoring for the Project’s construction works.
On the implementation of the SkyPier
Plan, the daily movements of all SkyPier HSFs in July
2016 were within the maximum daily cap number. A total of 836 HSF
movements under SkyPier Plan were recorded. All HSFs
had travelled through the SCZ with prevailing speed under 15 knots (8.0 to 14.8
knots) in compliance with the SkyPier Plan. Seven
ferry movements were not strictly following the diverted route. In
summary, the ET and IEC have audited the HSF movements against the SkyPier Plan and conducted follow up investigation or
actions accordingly.
Results of Impact Monitoring
All scheduled 1-hour total suspended
particulate (TSP), noise and waste monitoring were completed in the reporting
period for the relevant construction activities. No exceedance of the Action/
Limit Levels was recorded.
Summary of Upcoming Key Issues
The initial
reclamation works will commence on 1 August 2016. Major site activities anticipated
in the next reporting period for the Project will be under Contract P560(R)
including:
■ HDD pilot hole drilling;
■ Stockpiling of excavated materials
from HDD operation; and
■ Site clearance and construction
work at Sha Chau.
Site investigation
works will continuous to carry out to support design process. Deep Cement
Mixing (DCM) works contracts will be awarded in August 2016.
The key environmental issues will be associated
with dust and noise generation and construction waste management. The impact
water quality and Chinese White Dolphin (CWD) monitoring,
and ecological monitoring at Sha Chau will be commenced in August 2016. The
implementation of required mitigation measures by the Contractor will be
monitored by the ET.
Summary of Other Key Environmental Issues
The progress of
other related environmental surveys and baseline monitoring in this reporting
month are as follows:
Completed:
■ Baseline
monitoring of CWD by passive acoustic monitoring (PAM) has been completed in
July 2016.
Summary Table
The following table
summarizes the key findings of the EM&A programme during the reporting
period from 1 to 31 July 2016:
|
Yes |
No |
Details |
Analysis / Recommendation / Remedial Actions |
Breaches of Limit Level^ |
|
√ |
No exceedance of project-related limit level was recorded. |
Nil |
Breaches of Action Level^
|
|
√ |
No exceedance of project-related action level was recorded. |
Nil |
Complaints Received |
|
√ |
No construction activities related complaints were received. |
Nil |
Notification of any summons and status of prosecutions |
|
√ |
Neither notifications of summons nor prosecution were received. |
Nil |
Changes that affect the EM&A |
|
√ |
There were no changes to the construction works that may affect the EM&A |
Nil |
Remarks: ^
only exceedance of action/ limit level related to Project works will be
highlighted.
1
Introduction
|
On 7 November 2014, the Environmental Impact
Assessment (EIA) Report (Register No.: AEIAR-185/2014) for the “Expansion of
Hong Kong International Airport into a Three-Runway System” (the Project) was
approved and an Environmental Permit (EP) (Permit No.: EP-489/2014) was issued
for the construction and operation of the Project.
Airport Authority Hong Kong (AAHK) commissioned
Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental
Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A)
works during the construction phase of the Project in accordance with the
Updated EM&A Manual (the Manual) submitted under EP Condition 3.1.
The Manual is available on the Project’s dedicated website (accessible at: http://env.threerunwaysystem.com/en/index.html).
AECOM Asia Company Limited (AECOM) was employed by AAHK as the Independent
Environmental Checker (IEC) for the Project.
The Project covers the expansion of the
existing airport into a three-runway system (3RS) with key project components
comprising land formation of about 650 ha and all associated facilities and
infrastructure including taxiways, aprons, aircraft stands, a passenger
concourse, an expanded Terminal 2, all related airside and landside works and
associated ancillary and supporting facilities. The existing submarine
aviation fuel pipelines and submarine power cables also require diversion as
part of the works.
Construction of the
Project is to proceed in the general order of diversion of the submarine
aviation fuel pipelines, diversion of the submarine power cables, land
formation, and construction of infrastructure, followed by construction of
superstructures. The land-based construction works of the Contract P560(R)
Aviation Fuel Pipeline Diversion Works (Contract P560(R)) commenced on 28
December 2015 on the airport island.
The initial reclamation works will
commence on 1 August 2016. The overall phasing programme of all construction works has been updated
and is presented in Appendix A.
This is the 7th Construction Phase
Monthly EM&A Report for the Project which summarizes the key findings of
the EM&A programme during the reporting period from 1 to 31 July 2016.
The Project’s organization structure remained
unchanged during the reporting month. The Project’s organization structure and
the contact details of the key personnel can be referred to Appendix B and
Table 1.1 respectively of the Construction Phase Monthly EM&A
Report No.1.
During the reporting period, key
construction activities of the Project were related to the Contract P560(R)
Aviation Fuel Pipeline Diversion Works (Contract P560(R)) which involved
installation of horizontal directional drilling (HDD) casing and drilling of
HDD pilot hole at the HDD launching site located at the west part of the
airport.
The excavated materials from HDD
operation were stockpiled at the stockpile area located near Chun Ming Road
adjacent to Tradeport Logistic Centre on the airport
island.
The HDD launching site and stockpiling area are
around 3 km and 900m away respectively from the nearest air and noise sensitive
receivers in Tung Chung and the villages in North Lantau. The locations of the
Contract P560(R) works areas are presented in Figure
1. Site investigation works were carried out to support design process.
As presented in the Updated EM&A Manual,
the environmental aspects of interest for the Project include air quality,
noise, water quality, waste management, land contamination, terrestrial ecology,
marine ecology, fisheries, landscape & visual, sewage and sewerage, and
hazard to human life.
The status for all environmental
aspects is presented in Table 1.1. The
EM&A requirements remained unchanged during the reporting period and
details can be referred to Table 1.2 of the Construction Phase Monthly EM&A Report No. 1.
Table 1.1:
Summary of status for all environmental aspects under the Updated EM&A
Manual
Parameters |
Status |
Air Quality |
|
Baseline Monitoring |
The baseline air quality monitoring result has been reported in Baseline Monitoring Report (Version 1) and submitted to EPD on 14 December 2015 under EP Condition 3.4. |
Impact Monitoring |
On-going |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report (Version 1) and submitted to EPD on 14 December 2015 under EP Condition 3.4. |
Impact Monitoring |
On-going |
Water Quality |
|
General Baseline Water Quality Monitoring for reclamation, water jetting and field joint works |
The baseline water quality monitoring result has been reported in Water Quality Baseline Monitoring Report and submitted to EPD on 15 July 2016 under EP Condition 3.4. |
General Impact Water Quality Monitoring for reclamation, water jetting and field joint works |
To be commenced with the relevant construction works |
Initial Intensive Deep Cement Mixing (DCM) Water Quality Monitoring |
To be commenced with the relevant construction works |
Regular DCM Water Quality Monitoring |
To be commenced with the relevant construction works |
Waste Management |
|
Waste Monitoring |
On-going |
Land Contamination |
|
Supplementary Contamination Assessment Plan (CAP) |
To be submitted with the relevant construction works |
Contamination Assessment Report (CAR) for Golf Course |
The CAR for Golf Course was submitted to EPD on 17 March 2016. EPD had no adverse comment on the CAR for Golf Course on 6 April 2016. |
Terrestrial Ecology |
|
Pre-construction Egretry Survey Egretry Survey Plan |
The revised Egretry Survey Plan was submitted and approved by EPD on 25 April 2016 under EP Condition 2.14. |
Ecological Monitoring |
No construction work was carried out on Sheung Sha Chau Island during the ardeid’s breeding season in the reporting month in accordance with the Updated EM&A Manual. No ecological monitoring was conducted during the reporting month. |
Marine Ecology |
|
Pre-Construction Phase Coral Dive Survey |
The Coral Translocation Plan was approved by EPD on 6 June 2016 under EP Condition 2.12. |
Chinese White Dolphins (CWD) |
|
Vessel survey, land-based theodolite track and passive acoustic monitoring (PAM) |
|
Baseline Monitoring |
Baseline monitoring of CWD by passive acoustic monitoring (PAM) has been completed in July 2016.
The baseline CWD result has been reported in CWD Baseline Monitoring Report and submitted to EPD on 15 July 2016 under EP Condition 3.4. The CWD Baseline Monitoring Report has been approved by EPD on 25 July 2016. |
Impact Monitoring |
To be commenced with the relevant construction works |
Landscape & Visual |
|
Baseline Monitoring |
The baseline landscape & visual monitoring result has been reported in Baseline Monitoring Report (Version 1) and submitted to EPD on 14 December 2015 under EP Condition 3.4. |
Impact Monitoring |
On-going |
Environmental Auditing |
|
Regular site inspection |
On-going |
SkyPier High Speed Ferries (HSF) implementation measures |
On-going |
Construction and Associated Vessels Implementation measures |
To be commenced with the relevant construction works |
Complaint Hotline and Email channel |
On-going |
Environmental Log Book |
On-going |
Taking into account that the construction works
in this reporting month were mainly land-based works of Contract P560(R), the
required impact monitoring focused on air quality, noise, waste management and
landscape & visual. The EM&A programme also involved weekly site
inspections and related auditing conducted by the ET for checking the
implementation of the required environmental mitigation measures recommended in
the approved EIA Report.
The EM&A programme has
been following the recommendations presented in the approved EIA Report and the
Updated EM&A Manual. A summary of implementation status of the
environmental mitigation measures for the construction phase of the Project
during the reporting period is provided in Appendix B.
Air quality monitoring was conducted at two
representative monitoring stations in the vicinity of air sensitive receivers
in Tung Chung and villages in North Lantau in accordance with the Updated
EM&A Manual. Table 2.1 describes the
details of the monitoring stations. Figure 2
shows the locations of the monitoring stations.
Table 2.1:
Locations of Impact Air Quality Monitoring
Stations
Monitoring Station |
Location |
AR1A |
Man Tung Road Park |
AR2 |
Village House at Tin Sum |
In accordance with the Updated EM&A Manual, baseline 1-hour total suspended particulate (TSP)
levels at the two air quality monitoring stations were established as presented
in the Baseline Monitoring Report (Version 1 dated December 2015). Impact
1-hour TSP monitoring was conducted for three times every 6 days. The Action
and Limit Levels of the air quality monitoring are provided in Table 2.2. The air quality monitoring schedule
involved in the reporting period is provided in Appendix D.
Table 2.2:
Action and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AR1A |
306 |
500 |
AR2 |
298 |
Portable direct reading dust meter was used to
carry out the 1-hour TSP monitoring. The brand and model of the equipment
are given in Table 2.3.
Table 2.3:
Air Quality Monitoring Equipment
Equipment |
Brand and Model |
Portable direct reading dust meter (Laser dust monitor) |
SIBTA LD-3B-002 (Serial No. 974350) |
The measurement procedures involved in the
impact 1-hr TSP monitoring can be summarised as follows:
a. The portable direct reading dust
meter was mounted on a tripod at a height of 1.2 m above the ground.
b. Prior to the measurement, the equipment
was set up for 1 minute span check and 6 second background check.
c. The one hour dust measurement was
started. Site conditions and dust sources at the nearby area were recorded on a
record sheet.
d. When the measurement completed, the
“Count” reading per hour was recorded for result calculation.
The portable direct reading dust meter is
calibrated every year against high volume sampler (HVS) to check the validity
and accuracy of the results measured by direct reading method. The calibration
certificates of the portable direct reading dust meter are provided in Appendix C. The corresponding
calibration record of the HVS is also given in Appendix C.
The
monitoring results for 1-hour TSP are summarized in Table
2.4. Detailed impact monitoring results are presented in Appendix E.
Table 2.4:
Summary of 1-hour TSP Monitoring Results
Monitoring Station |
1-hr TSP Concentration Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AR1A |
2- 29 |
306 |
500 |
AR2 |
2- 28 |
298 |
No exceedance of the Action /Limit Level was
recorded at all monitoring stations in the reporting period.
General meteorological conditions throughout
the impact monitoring period were recorded. Wind data for each monitoring day
including wind speed and wind direction was collected from the Chek Lap Kok Wind Station.
Noise monitoring was conducted at five
representative monitoring stations in the vicinity of noise sensitive receivers
in Tung Chung and villages in North Lantau in accordance with the Updated
EM&A Manual. Figure 2 shows the
locations of the monitoring stations and these are described in Table 3.1 below. As described in Section 4.3.3 of
the Updated EM&A Manual, monitoring at NM2 will commence when the future
residential buildings in Tung Chung West Development become occupied.
Table 3.1:
Locations of Impact Noise Monitoring Stations
Monitoring Station |
Location |
Type of measurement |
NM1A |
Man Tung Road Park |
Free field |
NM2(1) |
Tung Chung West Development |
To be determined |
NM3A |
Site Office |
Facade |
NM4 |
Ching Chung Hau Po Woon Primary School |
Free field |
NM5 |
Village House in Tin Sum |
Free field |
NM6 |
House No. 1, Sha Lo Wan |
Free field |
Note: (1) As described in Section
4.3.3 of the Updated EM&A Manual, noise monitoring at NM2 will only
commence after occupation of the future Tung Chung West Development.
In accordance with the Updated EM&A Manual,
baseline noise levels at the noise monitoring stations were established as
presented in the Baseline Monitoring Report (Version 1 dated December 2015).
Impact noise monitoring was conducted once per week in the form of 30-minute
measurements of Leq, L10 and L90 levels
recorded at each monitoring station between 0700 and 1900 on normal weekdays.
The Action and Limit levels of the noise monitoring are provided in Table 3.2. The construction noise monitoring
schedule involved in the reporting period is provided in Appendix D.
Table 3.2:
Action and Limit Levels for Construction Noise
Monitoring Stations |
Time Period |
Action Level |
Limit Level, Leq(30mins) dB(A) |
NM1A, NM2, NM3A, NM4, NM5 and NM6 |
0700-1900 hours on normal weekdays |
When one documented complaint is received from any one of the sensitive receivers |
75 dB(A)(i) |
Note: (i) reduce to 70dB(A) for
school and 65dB(A) during school examination periods.
Noise monitoring was performed using sound
level meter at each designated monitoring station. The sound level meters
deployed comply with the International Electrotechnical
Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1)
specifications. Acoustic calibrator was used to check the sound level
meters by a known sound pressure level for field measurement. The brand
and model of the equipment are given in Table 3.3.
Table 3.3:
Noise Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound Level Meter |
B&K 2238 (Serial No. 2800932) B&K 2238 (Serial No. 2684503) B&K 2238 (Serial No. 2381580) |
Acoustic Calibrator |
B&K 4231 (Serial No. 3003246) B&K 4231 (Serial No. 3004068) |
The monitoring procedures involved in the noise
impact monitoring can be summarised as follows:
a. The sound level meter was set on a
tripod at least a height of 1.2 m above the ground for free-field measurements
at monitoring stations NM1A, NM4, NM5 and NM6. A correction of +3 dB(A) was applied to the free field measurements.
b. Façade measurements were made at the
monitoring station NM3A.
c. Parameters such as frequency
weighting, time weighting and measurement time were set.
d. Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator. If
the difference in the calibration level before and after measurement was more
than 1 dB(A), the measurement would be considered
invalid and repeat of noise measurement would be required after re-calibration
or repair of the equipment.
e. During the monitoring period, Leq,
L10 and L90 were recorded. In addition, site
conditions and noise sources were recorded on a record sheet.
f. Noise measurement results were
corrected with reference to the baseline monitoring levels.
g. Observations were recorded when high intrusive
noise (e.g. dog barking, helicopter noise) was observed during the monitoring.
The maintenance and calibration procedures are
summarised below:
a. The microphone head of the sound
level meter was cleaned with soft cloth at regular intervals.
b. The meter and calibrator were sent
to the supplier or laboratory accredited under Hong Kong Laboratory
Accreditation Scheme (HOKLAS) to check and calibrate at yearly intervals.
Calibration certificates of the
sound level meters and acoustic calibrators used in the noise monitoring are
provided in Appendix C.
The construction noise monitoring results are
summarized in Table 3.4 and
the detailed monitoring data are provided in Appendix E.
Table 3.4: Summary
of Construction Noise Monitoring Results
Monitoring Station |
Noise Level Range, dB(A) Leq (30 mins) |
Limit Level, dB(A) Leq (30 mins) |
NM1A(i) |
65- 72 |
75 |
NM3A |
61- 65 |
75 |
NM4(i) |
63- 66 |
70(ii) |
NM5(i) |
53- 58 |
75 |
NM6(i) |
62- 74 |
75 |
Note:
(i) +3 dB(A) Façade
correction included;
(ii) Reduced to 65 dB(A) during school examination
periods.
As the construction activities were small in
scale during the reporting period and far away from the monitoring stations,
major sources of noise dominating the monitoring stations observed during the
construction noise impact monitoring were aircraft noise at NM3A and NM5,
aircraft noise and helicopter noise at NM6, road traffic noise at NM1A and
school activities at NM4 in this reporting month.
No exceedance of the Action/ Limit Level was
recorded at all monitoring stations in the reporting period.
In accordance with the Updated EM&A Manual,
the waste generated from construction activities was audited once per week to
determine if wastes are being managed in accordance with the Waste Management
Plan (WMP) prepared for the Project, contract-specific WMP, and any statutory
and contractual requirements. All aspects of waste management including waste
generation, storage, transportation and disposal were assessed during the
audits. The Action and Limit levels of the construction waste are provided in Table 4.1.
Table 4.1:
Action and Limit Levels for Construction Waste
Monitoring Stations |
Action Level |
Limit Level |
Construction Area |
When one valid documented complaint is Received |
Non-compliance of the WMP, contract-specific WMPs, any statutory and contractual requirements |
Weekly monitoring of the Project construction
works was carried out by the ET on 6, 14, 20 and 27 July 2016 to check and
monitor the implementation of proper waste management practices during the
construction phase.
For Contract P560(R) Aviation Fuel
Pipeline Diversion Works, recommendations were provided during monitoring
including proper plugging of drip tray to avoid any leakage on 6 July 2016,
replacement/ repair of broken drip tray on 20 July 2016. The contractor had
followed up with implementation of mitigation measures.
The P560(R) Contractor was advised
to properly maintain a recording system, maximize the reuse of C&D
materials and properly maintain site tidiness.
Based on the updated information, about 284 m3 excavated
materials were produced from the HDD launching site in
July 2016. The generated excavated materials were temporarily stored at storage
and stockpiling area at Chun Ming Road adjacent to Tradeport
Logistic Centre on the airport island. The excavated material will be reused in
the Project.
In addition, metals, paper and
plastic were recycled during the reporting month. 1.2 tonnes of general refuse
were disposed of to the West New Territories (WENT) Landfill in July 2016. No
Construction and Demolition (C&D) material was disposed off-site during the
reporting month. No exceedances of the Action and Limit Levels were recorded in
the reporting period.
Weekly site inspection of the construction
works was carried out by the ET on 6, 14, 20 and 27 July 2016 to monitor the
implementation of proper environmental pollution control and mitigation
measures for the Project. Site inspections were also conducted independently by
the Project’s Independent Environmental Checker (IEC) on 8 and 20 July 2016. Observations have been recorded in
the site inspection checklists and passed to the Contractor together with the
appropriate recommended mitigation measures where necessary.
The key observations from site
inspection and associated recommendations were related to the improvement of
efficiency of wastewater treatment facilities, proper maintenance of drip tray
and provision of wheel washing before leaving the construction site.
In addition, CNP compliance check
of the use of powered mechanical equipment during restricted hour was carried
out by the ET on 11 July 2016. The use of powered mechanical equipment was
complied with the requirements of CNP.
A summary of implementation status
of the environmental mitigation measures for the construction phase of the
Project during the reporting period is provided in Appendix
B.
The
Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier (the SkyPier Plan) has
been submitted to the Advisory Council on the Environment (ACE) for comment and
subsequently submitted to and approved by EPD in November 2015 under EP Condition
2.10. The approved SkyPier Plan is available on the
dedicated website of the Project. In the SkyPier
Plan, AAHK committed to implementing the mitigation measure of requiring high
speed ferries (HSFs) of SkyPier travelling between
HKIA and Zhuhai / Macau to start diverting the route with an associated speed
control across an area (i.e. Speed Control Zone (SCZ)) with high Chinese White
Dolphin (CWD) abundance. The route diversion and speed restriction at the
SCZ have been implemented since 28 December 2015.
Key audit findings for the SkyPier
HSFs travelling to/from Zhuhai and Macau against the requirements of the SkyPier Plan during the reporting period are summarized in
Table 5.1. The daily movements of all SkyPier HSFs
in July 2016 were within the maximum daily cap number. Status of compliance
with annual daily average of 99 movements will be further reviewed in the
annual EM&A Report.
In total, 836 ferry movements between HKIA SkyPier and Zhuhai / Macau were recorded in July 2016 and
the data are presented in Appendix H. The time spent for the SkyPier
HSFs travelled through the SCZ in July were presented in Figure 5-1. It will take 9.6 minutes to travel through the SCZ
when the SkyPier HSFs adopt the maximum allowed speed
of 15-knot within the SCZ. Figure
5-1 shows that all the SkyPier HSFs spent more than 9.6 minutes to travel through
the SCZ.
Figure 5‑1 Duration of
the SkyPier HSFs travelled through the SCZ for July
2016
Seven ferry movements were not strictly following the
diverted route as recorded on 1, 8, 9, 11, 12, 15 and 22 July 2016. Notices
were sent to the ferry operators and the investigation results revealed that
they were related to safety / emergency situations presented as follows:
■
Case on 1,
8, 9, 11, 12 and 15 July 2016: HSF captains reported that the deviations of routing were due to
strong tidal current. Ferry operators were requested
to provide further supporting evidence as justification. Follow up action will
be taken if valid reasons / supporting evidence cannot be provided.
■
Case on 22
July 2016: This case is under investigation.
Another deviation case of not strictly following the
diverted route on 21 June 2016 has been followed up. Investigation found that
the vessel captain required to give way to
floating obstructions including buoy, marine refuse and bamboo raft for safety
reason. After that, the HSF returned to the normal route following the SkyPier Plan.
Table 5.1:
Summary of Key Audit Findings against the SkyPier
Plan
Requirements in the SkyPier Plan |
1 July to 31 July 2016 |
Total number of ferry movements recorded and audited |
836
|
Use diverted route and enter / leave SCZ through Gate Access Points |
7 deviations (FO were requested to provide further supporting evidence for investigation)
|
Speed control in speed control zone |
All HSFs were within 15 knots (8.0 knots to 14.8 knots), which complied with the SkyPier Plan. The time used by HSF to travel through SCZ is presented in Figure 5-1. |
Daily Cap (including all SkyPier HSFs)
|
88 to 94 daily movements (within maximum daily cap - 125 daily movements) |
The current status of submissions under the EP
up to the reporting period is presented in Table
5.2.
Table 5.2:
Status of Submissions under Environmental Permit
EP Condition |
Submission |
Status |
2.1 |
Complaint Management Plan |
Accepted / approved by EPD
|
2.4 |
Management Organizations |
|
2.5 |
Construction Works Schedule and Location Plans |
|
2.7 |
Marine Park Proposal |
|
2.8 |
Marine Ecology Conservation Plan |
|
2.9 |
Marine Travel Routes and Management Plan for Construction and Associated Vessels |
|
2.10 |
Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier |
|
2.11 |
Marine Mammal Watching Plan |
|
2.12 |
Coral Translocation Plan |
|
2.13 |
Fisheries Management Plan |
|
2.14 |
Egretry Survey Plan |
|
2.15 |
Silt Curtain Deployment Plan |
|
2.17 |
Detailed Plan on Deep Cement Mixing |
|
2.16 |
Spill Response Plan |
|
2.19 |
Waste Management Plan |
|
3.1 |
Updated EM&A Manual |
|
3.4 |
Baseline Monitoring Report |
During the reporting period, environmental
related licenses and permits required for the construction activities were checked.
No non-compliance with environmental statutory requirements was recorded. The
environmental licenses and permits which are valid in the reporting month are
presented in Appendix F.
During the reporting period, no construction
activities related complaints were received.
During the reporting period, neither
notifications of summons nor prosecution were received.
Cumulative
statistics on complaints, notifications of summons and status of prosecutions
are summarized in Appendix G.
The
initial reclamation works will commence on 1 August 2016. Major site activities anticipated in the next reporting period for the
Project will be under Contract P560(R) including:
■ HDD pilot hole drilling;
■ Stockpiling of excavated materials
from HDD operation; and
■ Site clearance and construction
work at Sha Chau.
Site investigation works will
continuous to carry out to support design process. Deep Cement Mixing (DCM)
works contracts will be awarded in August 2016.
The key environmental issues for the Project in
the coming reporting period are expected to be associated with the construction
activities of P560(R) Contract and these include:
■
Generation of dust from
construction works;
■
Noise impact from
operating equipment and machinery on-site;
■
Generation of site
surface runoffs and wastewater from activities on-site;
■
Management of
stockpiles;
■
Sorting, recycling,
storage and disposal of general refuse and construction waste;
■
Management of chemicals
and avoidance of oil spillage on-site.
The impact water quality and CWD monitoring, and ecological monitoring at Sha Chau will be
commenced in August 2016. The implementation of required mitigation measures by
the Contractor will be monitored by the ET.
The impact water quality and CWD monitoring
will be commenced on 1 August 2016. A tentative schedule of the planned
environmental monitoring work in the next reporting period is provided in Appendix D.
The key construction activities of the Project
carried out in the reporting month were related to the Contract P560 Aviation
Fuel Pipeline Diversion which involved installation of HDD casing, drilling of
HDD pilot hole and stockpiling of excavated materials
from HDD operation. Dust suppression measures including wheeling
washing, watering and covering of excavated materials and establishment of site
hoarding have been implemented.
Construction dust, noise and waste monitoring
were carried out in the reporting period. No breach of the Action or Limit
Levels in relation to the air quality, construction noise and waste monitoring
were recorded in the reporting month. All site observations made by the
ET were recorded in the site inspection checklists and passed to the Contractor
together with the recommended follow-up actions.
On the implementation of the SkyPier
Plan, the daily movements of all SkyPier HSFs in July
2016 were within the maximum daily cap number. A total of 836 HSF
movements under SkyPier Plan were recorded. All HSFs
had travelled through the SCZ with prevailing speed under 15 knots (8.0 to 14.8
knots) in compliance with the SkyPier Plan. Seven
ferry movements were not strictly following the diverted route. In
summary, the ET and IEC have audited the HSF movements against the SkyPier Plan and conducted follow up investigation or
actions accordingly.